On Wednesday evening, October 14, representatives of Friendship Hose Company No. 1 presented an update on our proposed new fire station project to Orwigsburg Borough Council.
The presentation provided Council with an overview of the need for a replacement station, conceptual building designs and floor plans, the anticipated construction schedule, and our current project funding position.
Our existing station at 121 North Liberty Street has served the department for decades, but the building is outdated and no longer provides the space and facilities needed to support modern fire and emergency services. The proposed Station 56 would provide four apparatus bays, improved safety and support areas, offices, training and meeting space, and facilities for our members.
The updated November 2026 presentation reflects a projected total project budget of $5,873,330.73, compared with $5,303,146.92 in identified funding and commitments, leaving a remaining difference of $570,183.81. The identified funding includes Capital Campaign pledges that have not all been received. These estimates may change as design and planning continue.
Our anticipated next steps include design coordination in November, permitting and approvals in November and December, and a targeted January construction start, with construction estimated to take approximately 12 months. These dates remain subject to required approvals and project scheduling.
We believe it is important to keep our community informed throughout this process. We are sharing the presentation below so residents can review the conceptual plans, the projected costs and funding, and what comes next.
View the Borough Council presentation
We appreciate the continued support of Orwigsburg Borough Council, our residents, local businesses, and everyone helping move this project forward.
Preparing for the next 100 years of dedicated service.